Sample Timeline

This is a sample project timeline based on our current first availability. We may have earlier openings if a scheduled project is delayed or for smaller projects.

You may notice a break after discovery. We schedule discovery as soon as possible so that we can finalize the scope and pricing.  Here’s more information on our process.

The modification period is not fixed and will last as long as needed. See this article for more information on how long it takes to build a website.

discovery

Discovery Phase

Dec 31 - Jan 11 (2 weeks)

user

Client Revisions

Jan 14 - 18 (1 week)

design

Design Phase

Jan 21 - Feb 1 (2 weeks)

user

Client Revisions

Feb 4 - 8 (1 week)

design

Design Phase continued

Feb 11 - 22 (2 weeks)

user

Client Revisions

Feb 25 - Mar 1 (1 week)

development

Development Phase

Mar 4 - 22 (3 weeks)

user

Modification Period

Mar 25 - Apr 12 (3 weeks)*

development

Migration and Launch

Apr 15, dependent on Modification Period*