This is a sample project timeline based on our current first availability. We may have earlier openings if a scheduled project is delayed or for smaller projects.
Please review Our Process to see what’s involved in each stage.
The modification period is not fixed and will last as long as needed. See this article for more information on how long it takes to build a website.
Discovery Phase
Jan 25 - Feb 12 (3 weeks)
Design Phase
Feb 15 - Mar 26 (6 weeks)
Development Phase
Mar 29 - Apr 16 (3 weeks)
Modification Period
Apr 19 - 30 (2 weeks)*
Migration and Launch
May 3, dependent on Modification Period*